Penerapan Metode Earned Value Dalam Analisis Kinerja Biaya Dan Waktu Pada Proyek Konstrusksi Sports Center Smk Bhakti Kartini Kecamatan Rawalumbu, Kota Bekasi

Authors

  • M. Fanshurullah Asa Universitas Pertamina
  • Alditya Riefqi Izzathamma Universitas Pertamina

DOI:

https://doi.org/10.55314/tsg.v5i3.810

Keywords:

Sports Center, Earned Value Method, Cost and Time Control, Project Performance

Abstract

Sports Center is a place consisting of activities and efforts that can help develop or foster a person's physical and spiritual potentials, whether in the form of games, matches, or just filling free time with sports. The Sports Center of SMK Bhakti Kartini located at Jl. Caringin no. 8, Kec. Rawalumbu, Bekasi City, West Java is one of the large 2-story Sports Centers, with various facilities such as a gymnasium, futsal with an international standard field, basketball, and various other facilities. In the construction of this Sports Center, there were many problems with delays in its construction, therefore a study was needed to analyze cost and time control. One of the project management methods for controlling costs and time is the Earned Value method. The Earned Value method is a method of managing a project by analyzing cost and time performance based on the weight of the plan, the weight of the realization, and the actual costs of the project. The results obtained using Ms. Excel, are the BCWS, ACWP, and BCWP values ​​in the 40th week are Rp. 3,088,884,893, Rp. 2,850,876,747, and Rp. 2,802,698,381. In addition to these variables, there are also variables of the Earned Value method for costs and time. The results of the calculation of project performance variables against costs obtained CV, CPI, ETC, and EAC values ​​in the 40th week were -Rp. 49,178,366, 0.983, Rp. 483,789,304, and Rp. 3,334,666,051. These results indicate that the project experienced cost overruns based on the calculations made. Project performance variables against time obtained SV, SPI, ETS, and EAS values ​​of -Rp.287,186,512, 0.91, 5.50  6 weeks, and 46 weeks. These results indicate that the project experienced a delay of ± 1 week from the planned schedule.

References

Agatha, & Drs. Hasan Dana, M.T. (2018). Pengendalian Biaya dan Jadwal Proyek Menggunakan Nilai Hasil (Rehabilitasi Gedung X Gresik).

Athalah, A. W. (2022). Analisis Pengendalian dan Percepatan pada Proyek Renovasi Gedung Panglima Polim 55. Jakarta: Universitas Pertamina.

Borges, A. C. (2024). Analisis Pengendalian Biaya dan Waktu Menggunakan Metode Nilai Hasil (Earned Value) Pada Kasus Pembangunan Gedung Puskesmas Lumbang Di Kabupaten Probolinggo. Jakarta: Universitas Pertamina.

Cibro, R. M. (2021). PERENCANAAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN RUMAH SUSUN PEKERJA INDUSTRI BATANG III BERBASIS BUILDING INFORMATION MODELING (BIM). Jakarta: Universitas Pertamina.

Damara. (2020). Cost Performance Analysis and Time Development Construction Project Bridge Chain Karanggeneng Nawacita Cs Using The Earned Value Method.

Desmi. (2011). Cost Performance Analysis and Time Development Construction Project Bridge Chain Karanggeneng Nawacita Cs Using The Earned Value Method.

Ginting, A. Y. (2023). Penerapan metode earned value dalam analisis kinerja biaya dan waktu pada proyek konstruksi fasilitas parkir & kantor administrasi RSU Vina Estetica . Jakarta: Universitas Pertamina.

Hidayat, & Marfuah, U. (2017). Penerapan Project Control Process dengan Metode Earned Value Manajemen Pada Proyek Pengadaan Kelambu Berinsektisida (Studi Kasus PT. Adiwara Worldwide).

Jamlaay. (2017). Kajian Kinerja Waktu dan Biaya Proyek dengan Metode Nilai Hasil (Earned Value) pada Laboratorium Navigasi Politeknik Perikanan Negeri Tual .

Janizar, Setiawan, F., & Rahmawati, R. (2021). Perkiraan Waktu dalam Penyelesaian Proyek Kolam Retensi Sirnaraga Menggunakan Penerapan EVA (Earned Value Analysis).

Juliana. (2016). Analisis Pengendalian Biaya dan Waktu pada Proyek Konstruksi dengan Metode Earned Value Management (EVM).

Larson, E. W. (1952). project management the managerial process.

Pabalik, Deane, R. W., & Pinkan, A. P. (2018). Analisis Nilai Hasil Terhadap Waktu pada Proyek Konstruksi (Studi Kasus) Pembangunan) Gedung Laboratorium Fakultas Teknik Universitas Sam Ratulangi). Manado: Universitas Sam Ratulangi.

Pakpahan. (2023). AnalisisBiaya dan Waktu Konstruksi Pembangunan Lanjutan Apron Shelter melalui Pendekatan Project Management Body of Knowledge (PMBOK) (Studi Kasus: Landasan Udara Iswahjudi Madiun). Madiun.

Prasityo. (2016). Analisas Kinerja Biaya dan Waktu dengan Metode Nilai Hasil (Earned Value Analysis) Pada Pembangunan Gedung Islamic Center Kabupaten Kutai Barat. Kutai.

Priyo, & Indraga. (2015). Cost Performance Analysis and Time Development Construction Project Bridge Chain Karanggeneng Nawacita Cs Using The Earned Value Method.

S, D. R., Suharyanto, & Kistiani. (2017). Pengendalian Biaya dan Waktu Proyek Dengan Metode Konsep Nilai Hasil (Earned Value).

Sandriawan, Yuwono, & Prasetyo. (2021). Analisis Keterlambatan Proyek dengan Konsep Earned Value Analysis pada Proyek Instalasi Pipa Boiler PT XYZ Tbk.

Sari, & Salasa. (2023). Pengendalian Waktu dan Biaya dengan Metode Earned Value Analysis (Studi Kasus: Rekonstruksi Jalan Kabupaten Kutai Kertanegara). Kutai.

Sari, Hendriyani, I., & Elsa, A. (2021). Earned Value Analysis pada Proyek Pembangunan Gedung Arsip Kantor BPN.

Susanty, Luhung, A. P., & Sari, D. P. (2016). Analisis Kinerja Proyek Pembangunan Rumah Sakit Banyumanik II dengan Menggunaan Earned Value Analysis (EVA) dan Project Evaluation Review Technique (PERT).

Verma, K., P., & Dixit, R. K. (2014). Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal.

Warka, Handayani, T., & Asmina, D. (2015). Pengendalian Biaya dan Waktu pada Proyek Pembangunan Gedung J (Irma Utama) RSU Provinsi NTB Menggunakan Metode Earned Value.